Case Study: Healthcare
Dawsongroup Process and Climate Control
Customer Project/Pain
Our Customer had an issue with a chilled water circuit feeding critical scanning equipment. The existing cooling circuit was working but had suffered from regular intermittent problems in maintaining the desired temperature. As the problem had deteriorated they had to share another resource, and this meant juggling some and cancelling several appointments until this was resolved.

Action/Solution
Following a call from their Estates/Site Services department, we arranged an immediate site visit to look at the best solution. Whilst the existing unit was on a roof of the building we found another route at ground level and could run flexible hoses at a high level to the existing connections, we isolated the existing unit to enable the customer to consider longer-term options going forward. Equipment was prepared and dispatched from our local depot on the same day and our engineering and install teams were on site to complete enabling works ready to complete on arrival. The unit was connected, filled, and commissioned and once the site services team had completed their checks we handed over.
Outcome/Benefits
With the facility back up and running at 100%, the Trust was able to restart the unit and had only had to rearrange a small number of appointments from the previous day.
Our Customers Say…
”I like trust, transparency, good prices and partnership”
– Danny Roberts, Logistics Manager, National Veterinary Service
“You gave us the best option for what we wanted, it was the most complete unit,
– Ricky Rowett, AMRC Composites Centre
“Dawsongroup provided a unique customer support service for our requirements”
– Peter Greer, AstraZeneca
See Who We Have Helped
Case Study: Pharmaceutical
A major Pharmaceutical outsourcing company was experiencing ongoing issues with a critical part of their cooling plant, the unit in …Case Study: Data Centres
A long-standing facilities manager partner approached us on behalf of a client they supported in Central London.Case Study: Manufacturing
The customer manufactures a wide range of plastic storage containers for various applications.Case Study: Bakery
We supplied/installed a suitably sized glycol (air-cooled) chiller with on board pumps /tank along with low-temperature air handlers positioned internally.Case Study: Baked Savouries
One of our customers had concerns over staff welfare from March through to the end of September during the higher …Case Study: Dairy
Customer had experienced a major incident on site, which had resulted in the loss of some valuable storage space for …Case Study: Confectionary
The customer had major issues in their main packing area due to high ambient and humidity levels.Case Study: 3PL
Customer was currently operating mixed products in an ambient warehousing facility – they had the opportunity to take on a …Case Study: Automotive
Customer had secured a new contract which meant they needed to install various new manufacturing cells to their production area, …
Speak To An Expert