Case Study: Automotive

Dawsongroup Process and Climate Control

Customer Project/Pain

Customer had secured a new contract which meant they needed to install various new manufacturing cells to their production area, and this would put a strain on their central cooling system. They had determined they would need to change internal pipework and upgrade the current cooling system – this would take some months, incur major capex, and cause disruption to the existing business.

Process Cooling Unit | DGPCC

Action/Solution

One of our project engineers visited site to look at the issues they were facing and having completed a site survey with the site services team they found they could provide the required additional cooling to the new cells and also take some pressure off the existing operation which was running at capacity. We were able to price the for a suitably sized air-cooled water chiller, manifolds, hoses, bypasses, and ancillaries whilst on site and a written proposal was sent to the customer to present to the business for approval.

Outcome/Benefits

Once the go-ahead was received and with the selected hire kit readily available from our extensive fleet, we liaised with our client and agreed for a weekend install to minimise disruption to the customers existing production. The equipment was delivered via Hiab, installed, and commissioned by our specialist install team on the same day.

The major benefits for the customer was to allow them to take on an additional volume of work without major capex and no causing no disruption to existing productivity. The hired equipment was also taking some pressure off the existing production.

SPEAK TO AN EXPERT TODAY

Our Customers Say…

”I like trust, transparency, good prices and partnership”

Danny Roberts, Logistics Manager, National Veterinary Service 

“You gave us the best option for what we wanted, it was the most complete unit,

Ricky Rowett, AMRC Composites Centre

“Dawsongroup provided a unique customer support service for our requirements”

Peter Greer, AstraZeneca

See Who We Have Helped

  • Case Study: Pharmaceutical

    Case Study: Pharmaceutical

    A major Pharmaceutical outsourcing company was experiencing ongoing issues with a critical part of their cooling plant, the unit in …
  • Case Study: Healthcare

    Case Study: Healthcare

    Our Customer had an issue with a chilled water circuit feeding critical scanning equipment.
  • Case Study: Data Centres

    Case Study: Data Centres

    A long-standing facilities manager partner approached us on behalf of a client they supported in Central London.
  • Case Study: Manufacturing

    Case Study: Manufacturing

    The customer manufactures a wide range of plastic storage containers for various applications.
  • Case Study: Bakery

    Case Study: Bakery

    We supplied/installed a suitably sized glycol (air-cooled) chiller with on board pumps /tank along with low-temperature air handlers positioned internally.
  • Case Study: Baked Savouries

    Case Study: Baked Savouries

    One of our customers had concerns over staff welfare from March through to the end of September during the higher …
  • Case Study: Dairy

    Case Study: Dairy

    Customer had experienced a major incident on site, which had resulted in the loss of some valuable storage space for …
  • Case Study: Confectionary

    Case Study: Confectionary

    The customer had major issues in their main packing area due to high ambient and humidity levels.
  • Case Study: 3PL

    Case Study: 3PL

    Customer was currently operating mixed products in an ambient warehousing facility – they had the opportunity to take on a …
VIEW ALL

Speak To An Expert