Case Study: Baked Savouries

Dawsongroup Process and Climate Control

Customer Project/Pain

One of our customers had concerns over staff welfare from March through to the end of September during the higher ambient period and they were experiencing problems in several areas of the factory. The existing cooling system was not coping in the warmer months, and we were approached to look at a viable solution.

Process Cooling Unit | DGPCC

Action/Solution

Our local project manager attended, met with all interested parties, and completed a thorough site survey to ensure we understood the issues and implications to the business.

On inspection, it was apparent that although the existing plant had been well maintained, age and additional internal heat loads added over time meant that is was struggling during the warmer months. Working with the engineering and production teams we came up with a viable solution to provide supplementary cooling to three areas that were those causing the most concerns and a backup plan for two other areas that were less of an issue but may change in the future.

We provided a written proposal for the temporary equipment, ancillaries, installation/strip out and transport cost and this was submitted later that day.

Order received and install dates and all enabling works planned/agreed to minimise disruption on site.

Outcome/Benefits

The equipment was installed and commissioned by our engineering support team and working with their production teams site suffered no loss to production. The supplementary equipment ensured all areas were maintained at a comfortable working environment even during days when the highest ambient temperatures prevailed. The customer enjoys the benefit of our inclusive 24/7, 365 maintenance cover during the hire period.

Our Customers Say…

”I like trust, transparency, good prices and partnership”

Danny Roberts, Logistics Manager, National Veterinary Service 

“You gave us the best option for what we wanted, it was the most complete unit,

Ricky Rowett, AMRC Composites Centre

“Dawsongroup provided a unique customer support service for our requirements”

Peter Greer, AstraZeneca

See Who We Have Helped

  • Case Study: Pharmaceutical

    Case Study: Pharmaceutical

    A major Pharmaceutical outsourcing company was experiencing ongoing issues with a critical part of their cooling plant, the unit in …
  • Case Study: Healthcare

    Case Study: Healthcare

    Our Customer had an issue with a chilled water circuit feeding critical scanning equipment.
  • Case Study: Data Centres

    Case Study: Data Centres

    A long-standing facilities manager partner approached us on behalf of a client they supported in Central London.
  • Case Study: Manufacturing

    Case Study: Manufacturing

    The customer manufactures a wide range of plastic storage containers for various applications.
  • Case Study: Bakery

    Case Study: Bakery

    We supplied/installed a suitably sized glycol (air-cooled) chiller with on board pumps /tank along with low-temperature air handlers positioned internally.
  • Case Study: Dairy

    Case Study: Dairy

    Customer had experienced a major incident on site, which had resulted in the loss of some valuable storage space for …
  • Case Study: Confectionary

    Case Study: Confectionary

    The customer had major issues in their main packing area due to high ambient and humidity levels.
  • Case Study: 3PL

    Case Study: 3PL

    Customer was currently operating mixed products in an ambient warehousing facility – they had the opportunity to take on a …
  • Case Study: Automotive

    Case Study: Automotive

    Customer had secured a new contract which meant they needed to install various new manufacturing cells to their production area, …

Speak To An Expert