Case Study: Data Centres
Dawsongroup Process and Climate Control
Customer Project/Pain
A long-standing facilities manager partner approached us on behalf of a client they supported in Central London. High ambient temperatures in the capital were causing major issues and with the existing cooling system struggling to maintain the required temperature in their server rooms they were facing almost certain expensive and damaging outages.

Action/Solution
We immediately arranged an on-site meeting with all parties to determine the best solution. The main issue was accessing along with the usual high-security issues associated with the location and nature of the business. With no available space on the roof, our best option for rapid deployment was to use a 130kw Chiller/Air Handling system, sited at ground level and run ducting to the rooftop and support the existing condensers. Equipment was delivered later that day and our engineers installed and commissioned the system.
Outcome/Benefits
The quick response avoided costly downtime and the units provided sufficient supplementary cooling to fully support their existing system during the warmer months. With a potential major issue avoided this allowed the customer to continue to operate and time to consider a longer-term solution.
Our Customers Say…
”I like trust, transparency, good prices and partnership”
– Danny Roberts, Logistics Manager, National Veterinary Service
“You gave us the best option for what we wanted, it was the most complete unit,
– Ricky Rowett, AMRC Composites Centre
“Dawsongroup provided a unique customer support service for our requirements”
– Peter Greer, AstraZeneca
See Who We Have Helped
Case Study: Pharmaceutical
A major Pharmaceutical outsourcing company was experiencing ongoing issues with a critical part of their cooling plant, the unit in …Case Study: Healthcare
Our Customer had an issue with a chilled water circuit feeding critical scanning equipment.Case Study: Manufacturing
The customer manufactures a wide range of plastic storage containers for various applications.Case Study: Bakery
We supplied/installed a suitably sized glycol (air-cooled) chiller with on board pumps /tank along with low-temperature air handlers positioned internally.Case Study: Baked Savouries
One of our customers had concerns over staff welfare from March through to the end of September during the higher …Case Study: Dairy
Customer had experienced a major incident on site, which had resulted in the loss of some valuable storage space for …Case Study: Confectionary
The customer had major issues in their main packing area due to high ambient and humidity levels.Case Study: 3PL
Customer was currently operating mixed products in an ambient warehousing facility – they had the opportunity to take on a …Case Study: Automotive
Customer had secured a new contract which meant they needed to install various new manufacturing cells to their production area, …
Speak To An Expert